Japan's JERA Courts Anthropic and Meta for AI Data Centers Near Tokyo Power Plants
Japan's biggest power generator wants AI campuses built at its own stations to skip years of grid waits, as TEPCO reportedly plans 10.2 trillion yen in spending.

What to know
- JERA has opened talks with Anthropic, Meta and other U.S. technology companies about data centers near its Tokyo-area power plants, Nikkei reported, according to Reuters on Nov. 27.
- The model builds on a $15 billion, 400-megawatt campus that JERA, Dell Technologies and RHAELM plan beside JERA's Chiba Thermal Power Station, with phased operations from 2028.
- Tokyo Electric Power plans to invest 10.2 trillion yen through fiscal 2035, including 4.9 trillion yen for transmission, to draw large data centers, South Korea's JKN reported.
TOKYO
JERA, Japan's largest power generator, has started talks with Anthropic, Meta and other U.S. technology companies about building data centers near its power plants around Tokyo, the Nikkei business daily reported, according to a Reuters account published Nov. 27.
Yukio Kani, JERA's global chief executive and chair, said in a recent interview that the company is also in discussions with Amazon, Microsoft and Google, Reuters reported. In one version of the Reuters story, a JERA spokesperson said its partner RHAELM handles marketing and had told JERA it is talking with several hyperscalers, the industry term for the largest cloud operators; another copy said JERA had not responded. RHAELM was not immediately available for comment, and Anthropic, Meta, Amazon, Microsoft and Google did not immediately respond to Reuters' requests for comment.
The pitch is simple: put the computing next to the generator. A data center built inside a power station can take electricity directly, avoiding the need for large new transmission lines, Jiji Press reported when JERA unveiled its first such project.
A template from Chiba
The talks extend a model JERA set out on Oct. 1, when it signed a memorandum of understanding with Dell Technologies and British developer RHAELM. The first project is a 400-megawatt-class hyperscale AI campus on land next to JERA's Chiba Thermal Power Station, east of Tokyo, with an estimated cost of about $15 billion, Reuters reported at the time.
Under that plan, JERA supplies land and up to 400 megawatts of power for 15 to 25 years, RHAELM develops, builds, operates and finances the site, and Dell provides standardized rack-scale AI systems. Apollo Global Management plans to act as an investment and financing partner for RHAELM. Phased operations are due to begin in 2028, with full capacity expected in 2029, according to Reuters.
The Chiba station runs on liquefied natural gas and has a total maximum output of 4.38 gigawatts, Data Center Dynamics reported. JERA has more than 20 sites that could host similar projects, the outlet said, and the partners want a footprint of several gigawatts across Japan in the 2030s. Kani said in October that “JERA is uniquely positioned to power Japan's AI ambitions,” The Next Web reported.
RHAELM Chief Executive Bradd Lewis argued at the launch that a power-plant site cuts the waiting time sharply. By co-locating at Chiba, he said, “we can deliver a 400MW facility years ahead of a conventional grid-connected timeline,” according to Data Center Dynamics.
The Financial Times estimated that the broader program could reach $140 billion, The Next Web reported, a figure JERA has not confirmed. JERA says it generates about a third of Japan's electricity, according to The Next Web, and it is jointly owned by Tokyo Electric Power Co. Holdings and Chubu Electric Power, Jiji Press and Reuters reported.
TEPCO plans a bigger bill, JKN reports
JERA's push landed on the same day as reports of a far larger spending plan from one of its two owners. TEPCO intends to invest 10.2 trillion yen in AI-related infrastructure through fiscal 2035 to attract large data centers, South Korean business daily JKN reported on Nov. 27.
Of that sum, 4.9 trillion yen would go to expanding transmission networks and 2.5 trillion yen to nuclear generation, with cumulative spending expected to pass 15 trillion yen by fiscal 2040, according to JKN. The utility is targeting facilities from large U.S. cloud companies such as Amazon Web Services and is pushing for rates above standard tariffs for those customers.
The money has a second purpose. TEPCO wants revenue from data centers to help cover decommissioning and compensation at the Fukushima Daiichi plant, which JKN put at about 500 billion yen a year. The company is negotiating capital partnerships with five groups, including SoftBank, KKR and Blackstone, the report said.
JKN reported that TEPCO expects peak demand in its service area to rise by about 4 million kilowatts by fiscal 2035, driven by data centers and chip plants. Contracted power for data centers alone is projected to climb by about 12 million kilowatts around fiscal 2037. The nuclear spending ties into Japan's slow reactor restarts, which Capital Times explained in Japan's Nuclear Restarts Explained.
What to watch
The Nikkei report describes talks, not contracts. The first signal will be whether any of the named companies signs as an anchor tenant at Chiba or another JERA site, since RHAELM is marketing that capacity now and the 2028 start leaves little slack for design and equipment orders.
Supply of AI hardware is a second test. Nvidia's move to halt server shipments to four Southeast Asian markets, covered in Nvidia Halts AI Server Shipments to Four Southeast Asian Markets, shows how quickly U.S. export rules can reshape where data centers get built in Asia.
Investors should also watch TEPCO's partnership talks and any formal release of its investment plan, which would show how much of the grid bill outside capital will carry and how much could land on electricity rates.
Sources
- AsiaOne (Reuters): Japan's JERA enters talks with Anthropic, Meta to build data centres, Nikkei reports (Nov. 27, 2026)
- Arab News (Reuters): Japan's JERA enters talks with Anthropic, Meta to build data centers, Nikkei reports (Nov. 27, 2026)
- JKN: TEPCO to Invest 10 Trillion Yen by 2035 to Attract Data Centers (Nov. 27, 2026)
- KSL.com (Reuters): JERA teams up with Dell, RHAELM on Japan's AI infrastructure, building data centre near Tokyo (Oct. 1, 2026)
- Data Center Dynamics: Jera, Dell Technologies, and Rhaelm team up for behind-the-meter AI infrastructure in Japan (Oct. 1, 2026)
- The Next Web: Japan eyes $140bn AI data centre push with Dell and JERA, FT reports (Oct. 1, 2026)
- Nippon.com (Jiji Press): JERA to Build Large AI Data Center near Tokyo (Oct. 2, 2026)
Our standards: Capital Times reports under the principles set out in our Editorial Standards and Ethics Policy. Spotted an error? Report it to our editors.