    Taiwan Sets Dec. 25, 2027 Opening for Taoyuan Airport's US$4.3 Billion Terminal 3

    The terminal is 91% built and will add room for 45 million passengers a year as Taoyuan heads for a record of more than 50 million in 2026.

    Share on X LinkedIn WhatsApp
    Terminal 3 under construction at Taiwan Taoyuan International Airport, seen from the observation deck
    Terminal 3 under construction at Taiwan Taoyuan International Airport in May 2026. Photo: 4300streetcar via Wikimedia Commons, CC BY 4.0

    What to know

    • Transportation Minister Chen Shih-kai said on Nov. 24 that Taoyuan Airport's Terminal 3 will open Dec. 25, 2027, after a trial run in November 2027.
    • The NT$128.4 billion (US$4.3 billion) terminal is about 91% complete, its operator says, and will add capacity for 45 million passengers a year.
    • Taoyuan handled 47.8 million passengers in 2025 and expects more than 50 million in 2026, a record, according to its operator.

    TAIPEI

    Taiwan has put a date on the new terminal at its main gateway. Taoyuan International Airport's Terminal 3 will open on Dec. 25, 2027, Transportation Minister Chen Shih-kai said on Nov. 24, after a trial run planned for November of that year.

    Chen gave the date during an inspection of the terminal's main facilities, according to the Central News Agency. He said construction “remains on schedule.” Taoyuan International Airport Corp., the state-owned operator, puts the project at about 91% complete.

    The timetable matters for airlines and investors because Taoyuan is running out of room. The operator said in a Nov. 22 statement that the airport handled 47.8 million passengers in 2025 and is expected to pass 50 million in 2026, which would be a record. CNA reported in June that, according to the Ministry of Transportation and Communications, the airport handled 21.64 million passengers in the first five months of this year, up 11% from a year earlier, with transfer traffic and cargo also growing at double-digit rates.

    A US$4.3 billion bet on transfer traffic

    The terminal costs NT$128.4 billion (US$4.3 billion), according to figures CNA reported in June, and will add capacity for 45 million passengers a year. Together with Terminals 1 and 2, that lifts the airport's total capacity to about 90 million.

    It will mainly serve Taiwan's three large carriers: China Airlines, EVA Air and Starlux Airlines. Plans reported in June call for 21 contact gates, five gates for smaller aircraft and a direct link to the airport MRT line. The design came from a team led by the late British architect Richard Rogers, with a wave-shaped roof held up by 16 steel columns.

    Automation is a central part of the pitch. The terminal will have 92 self-service check-in kiosks, close to half of its check-in positions, and an automated system that stores checked bags and routes them to the right flight. Chen said in June that travelers would be able to arrive three or four hours before departure and check in when it suits them, rather than waiting for airline counters to open.

    The operator's ambitions reach well beyond 2027. At the opening of the north concourse last December, President William Lai set 2045 targets for Taoyuan of 83 million passengers, 3.85 million tonnes of cargo and 435,000 takeoffs and landings. He also said finishing Terminal 3 would clear the way for work on a third runway.

    What is finished and what is left

    The main structure was completed in the first half of 2026, and crews have spent the second half on interiors. All 95,000 cloud-shaped ceiling panels are now installed, CNA reported, along with six check-in counter islands in part of the departure hall.

    The baggage hall is also done. It will have 12 carousels whose combined length matches every carousel in Terminals 1 and 2 put together, and the baggage handling system is complete.

    Most remaining hardware should be installed by early 2027. The harder part may be the handover. Preparing the terminal for service, which starts in the second half of 2027, involves coordinating 240 organizations and about 35,000 workers.

    Part of Terminal 3 is already in use. Its north concourse opened in December 2025 to ease early-morning congestion, with about 40 flights a day scheduled there, according to the Taipei Times. Passengers using it still clear immigration and security in Terminal 2 until the main building opens.

    Regional competition for connecting passengers

    Taoyuan's push comes as hubs across the region compete for transfer passengers. Hong Kong International Airport has been adding mainland transfer services to lift connecting traffic, as Capital Times reported this month, while Singapore's Changi posted only modest passenger growth in the third quarter, its latest figures showed.

    At the operator's annual forum on Nov. 13, OAG Aviation's head of Asia, Mayur Patel, forecast that Asia-Pacific airline capacity would grow 5.2% this winter season, against about 2% worldwide. He also flagged rising airline costs from Middle East tensions, oil prices and inflation.

    Airports Council International projects that Taiwan's passenger traffic will rise from 59.2 million in 2026 to 75.4 million in 2036, the operator said. Taoyuan executives have described the new terminal as the start of a new phase, with systems integration and staff training to follow ahead of the opening.

    For travelers, the immediate change is limited. Until late 2027 most flights will keep using the two existing terminals, and passengers on the north concourse will keep starting their journeys in Terminal 2.

    Sources

    1. Focus Taiwan (CNA): Taoyuan airport's Terminal 3 set to open Dec. 25, 2027: Minister (Nov. 24, 2026)
    2. Taoyuan International Airport Corp. via PR Newswire: Taoyuan Airport Forum Draws Global Expertise as Terminal 3 Preparations Advance (Nov. 22, 2026)
    3. Focus Taiwan (CNA): Taoyuan Airport Terminal 3 to boost automation, 2027 completion on track (June 16, 2026)
    4. Taipei Times: Front-page report on the opening of Terminal 3's north concourse at Taoyuan airport (Dec. 26, 2025)

    Capital Times Staff

    Capital Times newsroom, Hong Kong, Singapore and Jakarta

    Capital Times covers markets, business and economies across Asia.

    newsroom@capitaltimes.asia

    Our standards: Capital Times reports under the principles set out in our Editorial Standards and Ethics Policy. Spotted an error? Report it to our editors.

    Markets Data

    Hong Kong ClosedShanghai ClosedTokyo ClosedSeoul ClosedSingapore ClosedJakarta ClosedSydney ClosedMumbai Closed