Vietnam Signs $393 Million Design Deal for $67 Billion North-South High-Speed Rail
A French, Korean and Vietnamese consortium has 30 months to deliver the study that will decide how the 1,541-kilometer line is built and paid for.

What to know
- Vietnam's Thang Long Project Management Unit signed consultancy package TV-02 on Nov. 25 with an eight-member consortium led by France's SYSTRA.
- The contract is worth more than 10.24 trillion dong, about $393 million, and gives the consultants 30 months for surveys, the feasibility study, front-end design and tender documents.
- The 1,541-kilometer, 350-km/h line from Hanoi to Ho Chi Minh City carries a preliminary cost of about $67.34 billion and is meant to be substantially complete by 2035.
HANOI
Vietnam has hired the engineers who will decide what its most expensive infrastructure project will look like. The Thang Long Project Management Unit, which works under the Ministry of Construction, signed consultancy package TV-02 for the North-South high-speed railway on Nov. 25 with a consortium led by France's SYSTRA, according to the Vietnam News Agency.
The contract is worth more than 10.24 trillion dong, or about $393 million, below the package's estimated price of more than 10.78 trillion dong, VietnamPlus reported on Nov. 24. The consultants have 30 months to carry out field surveys, write the feasibility study, produce a front-end engineering design (FEED) and prepare the tender documents for the construction packages that follow.
The study matters to investors because it will settle questions the government has left open: which technology to use, how the work is divided, and how much private money can be drawn in. Under the contract, the consortium must assess financing options and the project's viability, including whether public-private partnerships with domestic and foreign investors could work, VietnamPlus said.
Who won and how
SYSTRA leads a group of eight firms. Its Korean partners are Sambo Engineering, Yooshin Engineering and Korea National Railway. The four Vietnamese members are Transport Engineering Design Inc. (TEDI), its southern counterpart TEDI South, Transport Engineering Investment and Construction Consultant JSC (TRICC) and Hoang Long Construction and Consultant JSC.
The package was awarded through direct international appointment in a single-stage, single-envelope process, according to the Nov. 24 report. Surveys will be paid at fixed unit prices, while the feasibility study, design and tender documents are lump-sum work. The state news agency described TV-02 as the most critical consulting package in the project's preparation phase.
Deputy Construction Minister Bui Xuan Dung told the signing ceremony that the package is the top priority and must be tied to clear milestones, deliverables and monitoring. He said all parties must “strictly honour their contractual commitments and refrain from shifting responsibility,” VietnamPlus reported. He also called it the first time Vietnam has taken on a high-speed rail project of this size.
The contest drew wide early interest. More than 80 domestic and international consulting firms, from countries including Japan, China, Germany, France and Spain, attended a project roadshow on May 15, Vietnam Investment Review reported at the time.
A $67 billion line, and a slipping schedule
The railway would run about 1,541 kilometers on new double track from Ngoc Hoi station in Hanoi to Thu Thiem station in Ho Chi Minh City, passing through 15 provinces and cities. It is designed for speeds of 350 km/h on standard 1,435-millimeter gauge, with 23 passenger stations and five freight stations, according to VietNamNet. The preliminary cost is about $67.34 billion, and the line is meant to be substantially complete by 2035.
The consultant was picked later than planned. Officials said in May that they aimed to finish selecting the TV-02 contractor by June 2026, Vietnam Investment Review reported, and the signing came about five months after that.
The start of construction has also moved. In January, VnExpress reported that the government planned to break ground in December 2026, when the ministry hired Spanish consultancy Ineco to advise on the feasibility work, technology and standards. By September, the ministry was aiming to start construction in December 2027, VietnamPlus reported. The project board's working timetable allows from the fourth quarter of 2026 to the fourth quarter of 2028 for the feasibility study, its appraisal and approval, and groundbreaking. Provincial and city authorities are handling land clearance as separate projects, with a target of finishing in the fourth quarter of 2028.
Funding remains unsettled. Deputy Construction Minister Nguyen Danh Huy said in January that the state wants to mobilize private capital but that “it is not possible to transfer all risks to enterprises,” according to VnExpress. The ministry has also told agencies to give priority to domestically made goods and services for stations, rolling stock and equipment, in line with government policy, VietnamPlus reported in September.
What to watch
The first checkpoint is the interim feasibility report, which officials scheduled for June 2027 back when they expected to pick the consultant in June 2026, according to VietNamNet. That document should give the first firm view of costs, the technology choice and the split between state and private funding, all of which will shape opportunities for builders, steelmakers and equipment suppliers in Vietnam and abroad.
The project also feeds into Hanoi's push for faster growth. Lawmakers have set a growth target of at least 10% for 2027, and officials have called public investment the main lever for this year's goal, as Capital Times reported in a look at Vietnam's fourth-quarter growth push. Large-scale spending on the railway itself, however, will not begin until the feasibility study is approved.
Another test is whether the consortium holds to its 30-month clock. With the start of construction already pushed back once, any further delay in the feasibility study would push the line's 2035 completion target closer to the edge.
Sources
- VietnamPlus (Vietnam News Agency): Key consultancy contract for North-South high-speed railway project signed (Nov. 26, 2026)
- VietnamPlus (Vietnam News Agency): Vietnam-France-RoK consortium wins consulting package for North-South high-speed railway (Nov. 24, 2026)
- VietnamPlus (Vietnam News Agency): North-South high-speed railway project targets December 2027 groundbreaking (Sept. 10, 2026)
- VietNamNet: Vietnam unveils timeline for $67 billion high-speed railway (May 20, 2026)
- Vietnam Investment Review: International consultants eye Vietnam's North-South high-speed rail feasibility contract (May 16, 2026)
- VnExpress International: Vietnam selects Spanish firm to consult on North-South high-speed rail (Jan. 31, 2026)
Our standards: Capital Times reports under the principles set out in our Editorial Standards and Ethics Policy. Spotted an error? Report it to our editors.