    AirTrunk Lines Up Over 1 Gigawatt of Hunter Renewables for Its Kurri Kurri Data Center

    The exclusivity pact with European Energy covers 260 MW of solar, up to 350 MW of wind and 800+ MWh of batteries, but no power purchase deal is signed yet.

    Share on X LinkedIn WhatsApp
    An aerial view of the Hunter Valley in New South Wales
    The Hunter Valley in New South Wales. Photo: Dicklyon via Wikimedia Commons, CC BY 4.0

    What to know

    • AirTrunk and European Energy Australia signed an exclusivity agreement for a 260 MW solar project, an 800+ MWh battery and a wind farm of up to 350 MW in the Hunter-Central Coast Renewable Energy Zone.
    • The projects are meant to help supply AirTrunk's proposed Kurri Kurri campus, which lists total power consumption of 550.5 MW in its New South Wales planning application.
    • Solar and battery assets are expected to run from 2030 and wind from 2032, and the two companies have not yet signed a power purchase agreement.

    SYDNEY

    Data center operator AirTrunk has signed an exclusivity agreement with European Energy Australia to develop solar, wind and battery projects in the Hunter region of New South Wales that together could add more than a gigawatt of generation and storage, as it tries to show how its proposed Kurri Kurri campus would be powered.

    The deal, announced last week, puts a number on a question now hanging over every large data center plan in Australia: where the electricity comes from. Federal and state rules increasingly expect operators to bring new supply with them rather than draw on an already tight grid, and the answer affects how quickly new AI computing capacity can be built in the country.

    What AirTrunk and European Energy agreed

    According to AirTrunk's statement, the two companies will progress a 260-megawatt solar project, a battery of more than 800 megawatt-hours and a wind farm of up to 350 megawatts, all in the Hunter-Central Coast Renewable Energy Zone. The solar and wind projects add up to about 610 MW of generation, W.Media noted. AirTrunk counts the battery storage to reach its "more than a gigawatt" figure.

    The solar farm and battery are expected to start operating in 2030 and the wind farm in 2032. European Energy plans to connect the projects to Ausgrid's upgraded 132-kilovolt network in the zone, subject to approvals, technical assessments and final connection arrangements.

    The agreement stops short of a supply contract. The companies are "discussing a potential long-term power purchase agreement," AirTrunk said, and the Newcastle Herald reported that no such agreement has been signed. Neither side has named the project sites, the Herald and PV Tech both reported, and PV Tech said the length of the exclusivity period was not disclosed.

    "Digital growth must bring new energy with it," Robin Khuda, AirTrunk's founder and chief executive, said in the statement. The partnership builds on the 31 MW Mulwala Solar Farm in southern New South Wales, a European Energy project tied to AirTrunk that opened last week.

    A 550-megawatt campus on an old smelter site

    The renewables are aimed at AirTrunk's wider New South Wales needs, including a proposed campus on the former Hydro Aluminium smelter site at Loxford, near Kurri Kurri in the Cessnock area. The state planning application lists total power consumption of 550.5 MW, W.Media and PV Tech reported. The Newcastle Herald has described it as a A$3.7 billion project; AirTrunk's statement did not give a cost.

    Set against that load, the Hunter projects cover only part of the need, and AirTrunk says so. Sabooh Whitelaw, the company's associate vice president for energy, told the Herald that "more renewable generation and firming will be needed" for Kurri Kurri and the rest of its state portfolio. The wind farm is also due two years after AirTrunk's 2030 target to match all of its electricity use with renewables. The company said about 73% of its use was matched in fiscal 2026.

    Local opposition has centered on power. Cessnock City Council voted unanimously in October to object to the project and called for a national freeze on data center approvals until federal rules are in place, the Herald reported, with one council member warning the site would strain local supply. The council is not the consent authority; the state government will decide the application, which was lodged as a state significant development. The deal was announced a day after public submissions on the plan closed, the Herald reported.

    The Herald has also reported that the company may use the nearby Snowy Hydro gas peaking plant to fill gaps between renewable output and demand. AirTrunk says it will pay for its own grid connection and use air cooling rather than water.

    Why the rules are tightening

    Canberra expects new data centers to secure additional clean generation or storage to offset their demand, and the New South Wales Data Centre Guidelines expect operators to fund the extra supply and network infrastructure their projects require without shifting net costs onto households and businesses, AirTrunk's statement said.

    PV Tech reported that Prime Minister Anthony Albanese said in July that large data centers would be legally required to put at least as much renewable energy into the grid as they draw, with legislation targeted for early 2027. The publication also cited estimates that data centers use about 4% of grid-supplied electricity in New South Wales, a share forecast to reach 11% by 2030, and said New South Wales and Victoria host about 80% of the country's data center capacity.

    AirTrunk itself has said each extra gigawatt of data center demand likely needs about 3 to 4 GW of new renewable capacity to run around the clock, PV Tech reported. On that ratio, the Hunter projects would cover only part of the round-the-clock needs of a campus the size of Kurri Kurri.

    The pressure is not confined to New South Wales. On Nov. 9, AirTrunk outlined a separate campus proposal at Mickleham in Melbourne's north, saying it would fund the infrastructure needed to connect that site to Victoria's transmission network and was exploring support for new renewable projects. AirTrunk is also expanding abroad, having signed an agreement for two campuses in India's Andhra Pradesh. Across the region, operators are being pushed to arrange their own power, from SoftBank's plans in Malaysia to Singapore's plans for power imports and new gas plants.

    What comes next

    The immediate test is the state planning decision on Kurri Kurri, now that public submissions have closed. The second is whether the exclusivity agreement turns into a signed long-term power purchase agreement, and on what terms, before the federal data center energy legislation that PV Tech said is targeted for early 2027. Investors in Australian renewables developers will watch for the project sites and grid connection approvals on Ausgrid's network, which will determine whether the 2030 start dates hold.

    Sources

    1. AirTrunk: AirTrunk and European Energy Australia Advance >1 Gigawatt Hunter Renewables and Storage Partnership (Nov. 12, 2026)
    2. Newcastle Herald: AirTrunk lines up Hunter clean energy projects for Kurri Kurri data centre, but more needed (Nov. 11, 2026)
    3. PV Tech: Data centre operator AirTrunk secures exclusivity on 1GW Hunter solar, wind and storage projects in Australia (Nov. 12, 2026)
    4. W.Media: AirTrunk targets 610MW of new renewable generation in NSW (Nov. 12, 2026)
    5. AirTrunk: AirTrunk advances plans for proposed Mickleham data centre (Nov. 9, 2026)

    Capital Times Staff

    Capital Times newsroom, Hong Kong, Singapore and Jakarta

    Capital Times covers markets, business and economies across Asia.

    newsroom@capitaltimes.asia

    Our standards: Capital Times reports under the principles set out in our Editorial Standards and Ethics Policy. Spotted an error? Report it to our editors.

    Markets Data

    Hong Kong ClosedShanghai ClosedTokyo ClosedSeoul ClosedSingapore ClosedJakarta ClosedSydney ClosedMumbai Closed